Board approves US$142 million Mbengwe underground materials handling project

A crusher and conveyor decline will remove 41 haul trucks from the ramp, cutting underground diesel consumption by an estimated 62% and lifting hoisting capacity to 4.5 Mtpa.

Kitwe, Zambia ·

The board of Quintel Corporation Limited has approved a US$142 million investment in the second phase of the underground materials handling system at the Mbengwe Copper Complex in Zambia. The project comprises an underground crushing station, a 2.1 kilometre conveyor decline and associated ore handling infrastructure.

The system replaces truck haulage on the main decline with continuous conveying. Forty-one haul trucks will be removed from the ramp, underground diesel consumption is expected to fall by 62%, and underground hoisting capacity will increase from 3.1 Mtpa to 4.5 Mtpa.

Project parameters

  • Capital cost of US$142 million, funded from operating cash flow with no additional debt drawdown.
  • Commissioning targeted for the fourth quarter of 2027.
  • Underground capacity increases from 3.1 Mtpa to 4.5 Mtpa, supporting the transition to a 61% underground feed share by 2031.
  • Estimated reduction of 18 kt CO₂e a year in Scope 1 emissions, equal to approximately 11% of the complex’s direct emissions.
  • Ventilation demand falls with the truck fleet, reducing electrical load on the primary fans by an estimated 4.2 MW.
  • Peak construction workforce of 620, with a commitment that at least 70% is recruited within Copperbelt Province.

The decision follows an eighteen-month study and a trade-off assessment against three alternatives, including a shaft option that was rejected on schedule and capital intensity grounds despite a marginally lower long-run operating cost.

“This is the least exciting kind of capital project and one of the most valuable,” said Emeka Nwosu, Chief Operating Officer. “It takes diesel out of a confined space, it takes trucks off a ramp where our people walk, and it makes the second half of the mine plan cheaper than the first. There is nothing novel in it, which is exactly why we are confident in the estimate.”

Ends

Media enquiries

[email protected]

About QuintelCorp

Quintel Corporation Limited is a privately held mining group founded in 1996. It operates seven mines and two development projects across nine African countries, producing copper, gold, silver, manganese and bauxite, and employs 6,400 people directly with a further 3,100 contractors.

Forward-looking statements

This release contains forward-looking statements, including production guidance, project schedules, cost estimates and target dates. Forward-looking statements are subject to risks and uncertainties, including commodity price movements, operational performance, geological outcomes, regulatory decisions and logistics availability, and actual results may differ materially. Mineral resource and ore reserve figures are reported in accordance with the JORC Code (2012), or the SAMREC Code (2016) for South African assets, and are reviewed annually by an independent Competent Person.